Project Network and Activity
- Consider the following project network and activity times (in weeks):
- Identify the critical path.
- How much time will be needed to complete this project?
- Can activity D be delayed without delaying the entire project? If so, by how many weeks?
- Can activity C be delayed without delaying the entire project? If so, by how many weeks?
- What is the schedule for activity E?
- Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network:
- Find the critical path.
- What is the expected project completion time?
- Based only on the critical path, what is the estimated probability the project can be completed in 44 weeks as requested by the owner?
- Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 57 weeks for this calculation.
- What should the construction company tell the owner?
Chapter 10
- Westside Auto purchases a component used in the manufacture of automobile generators directly from the supplier. Westside’s generator production operation, which is operated at a constant rate, will require 1000 components per month throughout the year (12,000 units annually). Assume that the ordering cost are $25 per order, the unit cost is $2.50 per component, and annual holding cost are 20% of the value of the inventory. Westside has 250 working days per year and a lead time of 5 days. Answer the following inventory policy questions:
- What is the EOQ for this component?
- What is the reorder point?
- What is the cycle time?
- What are the total annual holding and ordering cost associated with your recommended EOQ?
- The manager at a local university bookstore wishes to apply the EOQ model to determine the respective order quantities for two products: ballpoint pens and mechanical pencils. The annual demand for pens and pencils is 1500 and 400, respectively. The ordering cost for each product is $20 per order and the wholesale price of a pen and pencil is $1.50 and $4, respectively. Assume the bookstore’s annual holding rate is 10% and that the bookstore operates 240 days per year.
- Determine the optimal order quantity and the order cycle time for each product. What is the total cost (summed over both products)?
- The bookstore orders the pens and pencils from the same supplier. If these two products had the same cycle time, the corresponding shipment consolidation would reduce the ordering cost to $15. How much money does the bookstore save by consolidating the orders for these two products? (Hint: By setting the cycle times equal, we have Q pens/(1500/240) = Q pencils/(400/240) or Q pens = 3.75Q pencils. Make this substitution into the combined cost equation so that it is a function only of Q pencils and apply equation (10.5) with the appropriate values to determine Q pencils (and subsequently Q pens).
- Nation-Wide Bus Lines is proud of its six-week bus driver-training program that it conducts for all new Nation-Wide drivers. As long as the class size remains less than or equal to 35, a six-week training program cost Nation-Wide $22,000 for instructors, equipment, and so on. The Nation-Wide training program must provide the company with approximately five new drivers per month. After completing the training program, new drivers are paid $1600 per month paid to each idle new driver as a holding cost necessary to maintain a supply of newly trained drivers available for immediate service. Viewing new drivers as inventory-type units, how large should the training classes be to minimize Nation-Wide’s total annual training and new driver idle-time cost? How many training classes should the company hold each year? What is the total annual cost associated with your recommendation?